A £300,000 playground for ages 2 to 12 will fill the empty Five Swimmers pit in Staines. Permission was granted on 12 November, with no start date yet.

The empty sunken pit in Staines Memorial Gardens could become a children’s playground. Councillors decide on Wednesday 11 November, and planning officers are recommending approval.

Updated 13 November: the playground has been approved. The Planning Committee considered it on 11 November and the decision notice granting permission, with five conditions, is dated 12 November. Our report on the decision has the conditions.

The pit once held the Five Swimmers statue, which was removed in 2022, and it now sits fenced off and empty. The council is the applicant, which is why application 26/00739/FUL goes to the Planning Committee. The meeting starts at 7pm.

What would be built

The officers’ report describes a play area for children aged 2 to 12, on about 261 square metres. It would include:

  • swings and a spinner bowl
  • a wheelchair carousel, which is a roundabout
  • a linear play trail and a play panel
  • a “talk and tumble” with a tunnel
  • bench seating and planting along the edges

The ground would be raised by about 0.7 metres with foamed concrete, so the playground sits level with the gardens around it. A 1.2 metre steel fence would replace the current railings. The surface would be rubber bonded aggregate, coloured to mark out the different zones.

Watercolour illustration of the proposed playground: a semicircular area with coloured surfacing, swings, a timber play trail, a small slide structure, benches and planting, labelled with zones for ages 2 to 4 and 4 to 12.
Illustrative layout from planning application 26/00739/FUL. The final equipment has not been fixed. Image: Spelthorne Borough Council planning papers.

The report says the submission does not include final drawings of the equipment. A planning condition would require those details before work starts.

How much, and who pays

The budget is £300,000 from the Community Infrastructure Levy, the charge paid by developers. The Environment and Sustainability Committee agreed the plan and that spending limit on 13 November 2025, subject to planning permission.

What people said

The council’s survey ran from 1 December 2025 to 11 January 2026 and drew 296 responses.

  • 247 said a playground would be a positive addition. 40 said no and nine were not sure.
  • 215 said they or their family would use it. 59 said no and 22 were not sure.

The planning application itself drew five letters of support, including one from the Staines Town Society. One asked for public toilets to be added or considered nearby. There was one letter of objection, which called the scheme a waste of money, said a playground already exists on Commercial Road and said green space was under threat.

Unlike the ball court plan for the gardens, which 74% of consultation replies opposed, this one is not on the grass. It sits inside the existing pit.

The worries that were raised

The council’s 2025 report recorded concerns from the police. They said the spot was out of public view, with limited lighting and CCTV, and could become an after-hours hotspot for antisocial behaviour. They also raised its closeness to the river for young children.

Surrey Police has not objected to the planning application, but the officers’ report passes on its advice: keep clear sightlines, avoid planting that hides people, and use vandal-resistant equipment. No lighting is proposed.

The site is partly in flood zones 2 and 3a. The Environment Agency has not objected, and the flood assessment says the playground is designed to be open and floodable.

What happened to the Five Swimmers

The 2025 report tells the story. The plant room that drove the fountain flooded in 2014 and could not be repaired. The statue stood idle until 2022, when it was taken away with structural defects and put into storage.

In 2024 a construction company offered it a home in the private gardens of a new development of flats in Staines. The report says it has been repaired and can be seen working there by the public.

What it means for you

  • It is now approved. Permission was granted on 12 November. You can read the papers on the meeting page.
  • There is no opening date. The report gives no start or finish date for the work.
  • It follows Staines Park. The park’s new play area was due to open in July, also paid for by the levy.