Spelthorne wants to accept a lower offer for the Summit Centre in Sunbury after three earlier sales fell through. Keeping it costs about £600,000 a year.
Overview
Spelthorne Borough Council is recommending the sale of the Summit Centre on Hanworth Road, Sunbury, for less than it was offered before. Sales agreed in 2025 and in July 2026 did not complete. Both new offers are “significantly below” the earlier ones, the council’s report says. Councillors decide on 30 November and 3 December.
The report was published on Wednesday in the papers for the Commercial Assets Sub-Committee on 23 November. The price and the buyer’s name are in confidential appendices.
Fourth attempt to sell
The council bought the Summit Centre in September 2019, to earn rent for front-line services. Councillors approved selling it in March and September 2025, and again in July 2026. None of those sales completed, the report says.
Knight Frank marketed the site again for five weeks in September and October. The report gives the result:
- 14 parties showed interest, all wanting to redevelop it for industry
- 7 looked at it in detail, including site visits
- 2 made offers
- the target price was £13 million to £15 million
In June the council’s marketing brochure invited offers “in excess of £16,000,000”.
The report blames the market. It points to higher borrowing costs, weaker demand from businesses and the conflict in the Middle East. Sites without planning permission have become harder to sell, it says. An independent valuation, kept confidential, supports the offer price.
What is on the site
The brochure describes 84,747 sq ft of offices and industrial units in four buildings, on about 4.49 acres beside junction 1 of the M3. It has 272 parking spaces.
The offices are mostly empty. A further tenant leaves in January 2027, which takes the empty space to 29,750 sq ft, the report says. Officers call those units “unlettable even with substantial capital investment”.
The small industrial units are let to local businesses on flexible leases, and a charity uses one. Two parts of the site belong to other owners who use their own buildings.
Why the council wants to sell now
Keeping the site would cost about £600,000 a year, the report estimates. The centre lost money in the year to March 2026, and its value has fallen significantly since 2019.
Officers also warn that an empty site brings problems. They mention abandoned vehicles and anti-social behaviour, and copper thefts “as already seen at vacant Council owned sites”.
Spelthorne is under government directions to sell its commercial property and cut its debt. The government-appointed commissioners “strongly support” this sale. The council’s finance chief says it will “produce a significant saving over the next 10 years” for West Surrey Council, which takes over in April 2027.
What it means for you
The report says the sale does not affect the businesses or the charity now using the site. Every buyer that showed interest wanted to redevelop it for industry. Any rebuilding would need planning permission, and the site is zoned for employment use.
Key dates
- Monday 23 November, 1.30pm: Commercial Assets Sub-Committee
- Monday 30 November: Corporate Policy and Resources Committee
- Thursday 3 December: full Council makes the final decision